AssignmentsGet Method

L

Langhorne

We want to extract timesheet data from Project Server (2003) to feed a
billing system. PS has what we need -- number of hours per person per
project per week. Is the "AssignmentsGet" method in the PDS SDK what we
want? Has anyone used it? Any tricks or issues to be aware of? It looks
relatively straightforward, but then again so did Project Server before I
started working with it... :)

TIA

- Langhorne
 
D

Dale Howard [MVP]

Langhorne --

I would suggest you post this question in the
microsoft.public.project.developer newsgroup, as you are more likely to get
an answer there. Hope this helps.
 
L

Langhorne

Done. Thanks.

Dale Howard said:
Langhorne --

I would suggest you post this question in the
microsoft.public.project.developer newsgroup, as you are more likely to get
an answer there. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top