At the time of tracking, why the resources units are increasing, .

M

Muralidhar

While scheduling the resource units have been assigned to 100%, but while
tracking the resource units have been changed to 200++%. Can any one explain
us elaborately.
 
J

Jan De Messemaeker

Hi,

When you enter as actual work for a resource in a day (for instance) 16
hours, that is 200%.
Project shows the largest percentage over the whole duration of the task.
IMHO this is absolutely wrong (Actuals should not change allocation%) but
I'm awfully sorry, taht is how it is done.
 