Hi

I have a business process automated to create and customise a WSS project
site(add various list items, change permissions etc). The process, among
other things, also creates a new project in project server using the project
server web services. I wish to set the WSS site of this new project to be
the WSS site created earlier but I can't seem to find the right methods to do
this. I can attach the site manually in the server settings but I would like
to do this automatically.

Can any one point me in the right direction?

Regards

Andrew
 
A

Andrew Stokes

Cheers Rod,

Having the site created during publish is the way to go. I was getting
carried away trying to get the 'UpdateProjectWorkspaceAddress' method to work
as I'd already written the create/customise site code.

Thanks for your help

Andrew
 