Hi All,
We have a Team Calendar (SharePoint 2007) which has all local public
holidays.
Now, instead of using "Enterprise Calendars" (Project Server 2007), we need
to attach "Team Calendar" (SharePoint).
I know we can do it on enterprise calendar itself but we have all our public
holidays in SharePoint. That's why, there would be reduntant data on Project
Server.
Could it be done? If yes, how can I do it?
Thanks!
Cheers,
Aroh