S
Scott McClure
Tried to post this earlier and it didn't seem to work.
Forgive me if you've seen it.
We continue to struggle with the circumstances under
which Project changes our Actual Work from the entered
values. We understand that it may split and move some
into the future because the calendar for the given
resource does not support as many hours as entered.
Still, there are other effects that we are not yet able
to understand.
Actual labor hours are collected from a Work Order system
and a report is produced from that system for entry into
project. This is done via the Task Usage view in Project
Pro. Because of changes we have made to the structure of
this project and the problems mentioned above, we are in
the process of auditing all of the labor (actual work)
entered to date from June.
The particular symptom I am asking about now is that the
last few days verified (the operator, and there is only
one, is working day by day) were not the same upon
opening the project as they were when the project was
closed. We do not allow any entry of this time via OWA
or by any of the other Pro users. Can anyone give us a
hint of the various things that may change the Actual
Work from the values entered?
TIA,
Scott
Forgive me if you've seen it.
We continue to struggle with the circumstances under
which Project changes our Actual Work from the entered
values. We understand that it may split and move some
into the future because the calendar for the given
resource does not support as many hours as entered.
Still, there are other effects that we are not yet able
to understand.
Actual labor hours are collected from a Work Order system
and a report is produced from that system for entry into
project. This is done via the Task Usage view in Project
Pro. Because of changes we have made to the structure of
this project and the problems mentioned above, we are in
the process of auditing all of the labor (actual work)
entered to date from June.
The particular symptom I am asking about now is that the
last few days verified (the operator, and there is only
one, is working day by day) were not the same upon
opening the project as they were when the project was
closed. We do not allow any entry of this time via OWA
or by any of the other Pro users. Can anyone give us a
hint of the various things that may change the Actual
Work from the values entered?
TIA,
Scott