HI,
My project schedule is few hundred lines.
i want to have the key taks as my summary in the top of my schedule.
i created them on top as "Project Key Items".
Now i want to Auto populate the % complete here based on the value from a task item from my detailed project schedule.
Example...
WBS TASK NAME %Complete
1.1. Project Key summary
1.1.1 Discovery Phase ------------ ??
1.1.2 Planning Phase
1.2 Discovery Phase --------------47%
1.2.1Task 1 ---------------------- 90%
1.2.2Task 2 ---------------------- 50%
1.2.3Task 3 ---------------------- 0%
Here for 1.1.1 the %Complete should be populated from 1.2 which is 47%.
How can this be achieved.
my email id is (e-mail address removed)
My project schedule is few hundred lines.
i want to have the key taks as my summary in the top of my schedule.
i created them on top as "Project Key Items".
Now i want to Auto populate the % complete here based on the value from a task item from my detailed project schedule.
Example...
WBS TASK NAME %Complete
1.1. Project Key summary
1.1.1 Discovery Phase ------------ ??
1.1.2 Planning Phase
1.2 Discovery Phase --------------47%
1.2.1Task 1 ---------------------- 90%
1.2.2Task 2 ---------------------- 50%
1.2.3Task 3 ---------------------- 0%
Here for 1.1.1 the %Complete should be populated from 1.2 which is 47%.
How can this be achieved.
my email id is (e-mail address removed)