J
JungleBoy
Hi
Some of the resources in our project serverare offshore and do not enter
time using Project web access. The project manager goes in the project and
updates the tasks , say 100% done or something. In some projects its ok but
some projects when he tries to save it after updates it gives a message to
"The project is not synced and should it synced to actuals" with no option to
cancel only OK. When he presses ok he looses the updates he did on behalf of
the resources. Any way to turn this option off, so that it does not give
message or sync to actuals like other projects.
Thanks
Some of the resources in our project serverare offshore and do not enter
time using Project web access. The project manager goes in the project and
updates the tasks , say 100% done or something. In some projects its ok but
some projects when he tries to save it after updates it gives a message to
"The project is not synced and should it synced to actuals" with no option to
cancel only OK. When he presses ok he looses the updates he did on behalf of
the resources. Any way to turn this option off, so that it does not give
message or sync to actuals like other projects.
Thanks