R
Ramana Murthy
Hi,
I have 2 MS Project Files, one is Activity Plan and another is Milestone
Plan. In Activity Plan i have defined tasks and Milestone plan i have defined
only milestones which are linked to the tasks in the Activity Plan
(Predecessors). Is there any way when i update Tasks in the Activity Plan, it
should autometically update the data in the Milestone plan with out opening
the file manually???
This has to be done using the Macro
It would be great, if i get any help ???
I have 2 MS Project Files, one is Activity Plan and another is Milestone
Plan. In Activity Plan i have defined tasks and Milestone plan i have defined
only milestones which are linked to the tasks in the Activity Plan
(Predecessors). Is there any way when i update Tasks in the Activity Plan, it
should autometically update the data in the Milestone plan with out opening
the file manually???
This has to be done using the Macro
It would be great, if i get any help ???