P
Peter Rooney
I want to customise my menu bar only when a certain plan is active (there is
a save option on the customisation, which I only want to be available when
the plan is visible, so as to prevent the user from overwriting the plan with
the wrong file)
I used to use Auto_Activate / Auto_Deactivate in Office 97, but they don't
appear to work in Project 2000. What's the correct format?
Incidentally, Autpen and Auto_Close DO work with Project 2000, although I
suspect there's a "proper" version of these too, if anybody would care to
enlighten me. I don't like "compromise" code!
Regards
Pete
a save option on the customisation, which I only want to be available when
the plan is visible, so as to prevent the user from overwriting the plan with
the wrong file)
I used to use Auto_Activate / Auto_Deactivate in Office 97, but they don't
appear to work in Project 2000. What's the correct format?
Incidentally, Autpen and Auto_Close DO work with Project 2000, although I
suspect there's a "proper" version of these too, if anybody would care to
enlighten me. I don't like "compromise" code!
Regards
Pete