C
chemicals
I have resources working on 5-10 "tasks" at any one time. I would like to
be able to:
1.) Write a macro to adjust resource units automatically based on a multi
week plan. i.e. every task has a rough plan where the I can preload the
resource showing that they will work on any task 50% the first week, 30% in
weeks 2-4, 80% in weeks 5-7, and 10% in week 8 - as an example?
Thanks
be able to:
1.) Write a macro to adjust resource units automatically based on a multi
week plan. i.e. every task has a rough plan where the I can preload the
resource showing that they will work on any task 50% the first week, 30% in
weeks 2-4, 80% in weeks 5-7, and 10% in week 8 - as an example?
Thanks