I have resources working on 5-10 "tasks" at any one time. I would like to
be able to:

1.) Write a macro to adjust resource units automatically based on a multi
week plan. i.e. every task has a rough plan where the I can preload the
resource showing that they will work on any task 50% the first week, 30% in
weeks 2-4, 80% in weeks 5-7, and 10% in week 8 - as an example?

Thanks
 
J

Jan De Messemaeker

Hi,

project 2000 is as good as any to do that.
Read the help on the Timescaledata method, you will find what you're after.
HTH
 
C

chemicals

Thanks. I have looked around for information on the Timescaled method but
everything references exports to Excel. I need to import a work plan for
each resource for each task. I don't see much infom on the actual method.

I want to be able to take a resource (B Smith) and assign them to task A, B,
and C.
Those tasks do not start at the same time but can run in parallel. I need
to import a monthly profile that for each task (A,B,orC) the assigned
resource will work 50%, 30%, 30%, 20%, and 40% for the 5 months the task will
take to complete......

I could do it all by hand but it seems perfect for a macro...(VBA)
 
J

Jan De Messemaeker

Hi,

Have you actually read the help (Object Browser) of the timescaledata
method? It doesn't even mention Excel, instead it gives you all the info you
need.
HTH
 