Looking for some help into an issue that comes up. Currently developing a
system where MS project 2007 pro automates tasks updates from a database with
actual start and end times, through task mappings. My problem now is that
when a resource is set to that task for 9am to 5pm, and the work is done
after hours (ie, 5:48 pm is the start database time, and 6:15pm is the end
time), MS project does not update with the actual start time, but sets it at
5pm and ending at 5pm, b/c that is when the resource works. So my work and
duration is zero, but in actual fact, they work a bit of overtime. Any ideas
how i can fix this?
Looking into this more, I can go into the project manually and change the
times myself to the correct times, but the work and duration are still zero.
Thanks for your time
James
Looking for some help into an issue that comes up. Currently developing a
system where MS project 2007 pro automates tasks updates from a database with
actual start and end times, through task mappings. My problem now is that
when a resource is set to that task for 9am to 5pm, and the work is done
after hours (ie, 5:48 pm is the start database time, and 6:15pm is the end
time), MS project does not update with the actual start time, but sets it at
5pm and ending at 5pm, b/c that is when the resource works. So my work and
duration is zero, but in actual fact, they work a bit of overtime. Any ideas
how i can fix this?
Looking into this more, I can go into the project manually and change the
times myself to the correct times, but the work and duration are still zero.
Thanks for your time