Automated updates not working due to resource calendar

J

j8chan

Hi all,

Looking for some help into an issue that comes up. Currently developing a
system where MS project 2007 pro automates tasks updates from a database with
actual start and end times, through task mappings. My problem now is that
when a resource is set to that task for 9am to 5pm, and the work is done
after hours (ie, 5:48 pm is the start database time, and 6:15pm is the end
time), MS project does not update with the actual start time, but sets it at
5pm and ending at 5pm, b/c that is when the resource works. So my work and
duration is zero, but in actual fact, they work a bit of overtime. Any ideas
how i can fix this?
Looking into this more, I can go into the project manually and change the
times myself to the correct times, but the work and duration are still zero.
Thanks for your time
James
 
G

Gary Chefetz

James:

The first thing that comes to mind is to post the work to Actual Overtime.
Another is to use a task calendar. With that said, it sounds as though you
need development help, and a better place for that would be the developer
group. To address your issues more rapidly, provide more specifics including
code samples when appropriate.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top