I'm not sure what you're saying is happening. Are you saying that if you
change the duration on one or more subtasks indented under a summary task,
the summary task's duration doesn't change? If so, that could be perfectly
normal behavior depending on the durations and linking of the subtasks. The
summary task duration is not the sum of the subtasks. It is the time
between when the earliest strting subtask begin's until the latest finishing
subtask ends. If your editing the durations does not affect the end date of
the latest ending task, the summary duration won't, and shouldn't, change.
Here's an example.
Summary Task, 15 days
Subtask1, 5 days
Subtask 2, 10 days, no predecessor
Subtask 3, 15 days, no predecessor
All three tasks start together and go in parallel. The duration of the
summary is 15 days. If I change the duration of subtask1 to 10 days, the
summary will not change. OTOH, if I change subtask3 to 18 days, the summary
*will* change.
Hope I've guessed right what is happening with your situation.
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hi guys
Here's one for you ...
My summary row doesn't seem to be calculating automatically? The column
contains duration fields. I have the options set to calculate
automatically
and all open projects.
I really don't want to manually calculate every time I change a value.
Can anyone help?
Niki