Hello,
I have a schedule in MS Project 2007 where I have the options set in
calculation mode to "Automatic" and calculate to "All Open Projects",
however, if I trace back the critical path using Task Drivers and eliminate a
driving predecessor, the software does not automatically calculate. It
changes the date on the task where I have deleted the predecessor, but does
not calculate the entire project. If I go into Options and manually
calculate it, it works fine. Has anyone else had this problem before?
Thanks for your help.
I have a schedule in MS Project 2007 where I have the options set in
calculation mode to "Automatic" and calculate to "All Open Projects",
however, if I trace back the critical path using Task Drivers and eliminate a
driving predecessor, the software does not automatically calculate. It
changes the date on the task where I have deleted the predecessor, but does
not calculate the entire project. If I go into Options and manually
calculate it, it works fine. Has anyone else had this problem before?
Thanks for your help.