Automatic Calculation

M

Melissa

Created a small project which is 10 days in duration. To solve overallocation - levelled. The Prject should now be 11 days duration, however it still displays 10 days. On pressing F9 key it updates to show 11 days. Anyone know why I have to do this? is there an option I need to switch on for this to happen automatically? In Tools>Options calcuate tab, it is set to automatic.
 
S

Steve House

Display the Project Summary task and make a note of the start & finish
dates and times. Level, note the new values. Press F9 and note the
values. What do you find?


--
Steve House
MS Project MVP
Visit http://www.mvps.org/project/faqs.htm for the FAQs

Melissa said:
Created a small project which is 10 days in duration. To solve
overallocation - levelled. The Prject should now be 11 days duration,
however it still displays 10 days. On pressing F9 key it updates to show
11 days. Anyone know why I have to do this? is there an option I need to
switch on for this to happen automatically? In Tools>Options calcuate
tab, it is set to automatic.
 