J
JCTP
Hi folks. Hope you can help me.
I´m working on a schedule and I´m having problems in resolving some
overallocations.
I have one task assigned to an analyst, and some support tasks
assigned also to him.
For example (considering 8 hours work by day)
Main_task is 32 hours work and 4 days duration
Support_task is 2 hours work and 2 hours duration.
Let's say that Support_task falls in the middle of the development of
Main_Task
What I´d like is to be able to automatically level the overallocation
that happens during that single day. Very much like what I can
manually do by editing the hours directly in the "Resource Usage" view
(manual countour).
By manually countouring I can get as a result, that Main_task will
last 5 days (34 hours).
Changing the units of the tasks will result in using less hours during
the whole duration of the task, increasing the duration of the task
more than two hours. In this example, If I change units for Main_task
to 80% I will be having 6.4 hours for the first days, even though
there was no overallocation there.
Thanks for any help
Juan Carlos
I´m working on a schedule and I´m having problems in resolving some
overallocations.
I have one task assigned to an analyst, and some support tasks
assigned also to him.
For example (considering 8 hours work by day)
Main_task is 32 hours work and 4 days duration
Support_task is 2 hours work and 2 hours duration.
Let's say that Support_task falls in the middle of the development of
Main_Task
What I´d like is to be able to automatically level the overallocation
that happens during that single day. Very much like what I can
manually do by editing the hours directly in the "Resource Usage" view
(manual countour).
By manually countouring I can get as a result, that Main_task will
last 5 days (34 hours).
Changing the units of the tasks will result in using less hours during
the whole duration of the task, increasing the duration of the task
more than two hours. In this example, If I change units for Main_task
to 80% I will be having 6.4 hours for the first days, even though
there was no overallocation there.
Thanks for any help
Juan Carlos