in April, 2005, you posted the following info on automatic deletion of
old tasks from timesheets to this user group:
Your Project Server administrator can easily delete completed tasks
from
each team member's timesheet in PWA by completing the following steps:
1. Log into PWA with administrator permissions
2. Click the Admin menu
3. Click the Clean up Project Server database link
4. Select the Tasks option
5. Click the Delete drop-down list and select Only completed task
assignments from the list
6. Select the drop-down list on the right and select the desired
deletion
option
7. At the bottom of the page, select whether to delete completed tasks
for
all resources or a single resource
8. Click the Delete button
my question: does this delete actuals in PWA / cube? i know the
actuals remain in Project 2003, but will my cube look like fewer hours
worked because i do this deletion??
pls advise.tx.jlg
in April, 2005, you posted the following info on automatic deletion of
old tasks from timesheets to this user group:
Your Project Server administrator can easily delete completed tasks
from
each team member's timesheet in PWA by completing the following steps:
1. Log into PWA with administrator permissions
2. Click the Admin menu
3. Click the Clean up Project Server database link
4. Select the Tasks option
5. Click the Delete drop-down list and select Only completed task
assignments from the list
6. Select the drop-down list on the right and select the desired
deletion
option
7. At the bottom of the page, select whether to delete completed tasks
for
all resources or a single resource
8. Click the Delete button
my question: does this delete actuals in PWA / cube? i know the
actuals remain in Project 2003, but will my cube look like fewer hours
worked because i do this deletion??
pls advise.tx.jlg