A
Arjan
Hi,
I noticed that when I change for example the maximum units from a resource,
I have to enter the Resource Leveling window and press 'Level Now' although
it shows it should level automatically according to the first radio button.
I have also an occassion that a task got split up and the only way to get it
sheduled really 'As soon as possible' was to remove the resource and assign
it again. (although duration said 4 days, work 8 hours and the resource was
assigned 25% units innitially the task was spread over several weeks)
I hope this is just something I don't master yet and someone can tell me how
it really works.
Thanks. Arjan.
I noticed that when I change for example the maximum units from a resource,
I have to enter the Resource Leveling window and press 'Level Now' although
it shows it should level automatically according to the first radio button.
I have also an occassion that a task got split up and the only way to get it
sheduled really 'As soon as possible' was to remove the resource and assign
it again. (although duration said 4 days, work 8 hours and the resource was
assigned 25% units innitially the task was spread over several weeks)
I hope this is just something I don't master yet and someone can tell me how
it really works.
Thanks. Arjan.