Hi All,

Does anyone have a script example of creating links between projects? What
I trying to build is a routine which queries the tasks in one project file
and creates a link to a successor task in another project file. This
routine will query using 'key' data found in the WBS and a Start to Start
link type. Lastly, The predecessor task is a milestone. Anyone done
anything similiar?

Dave
 
R

Rod Gill

Hi,

Record a macro of you linking tasks in two different files. This will give
you a starting point for the rest of your code.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 