Hello,
I'm just starting out with MS project 2007 and I have something I can'
get right.
I have already
- Created my resources and stated how many % they are available fo
the project, e.g. 40% (2 days per week)
- Listed all my tasks
- Added an estimate of how many hours a task would take in the wor
column (I didn't touch the duration, start or finish columns)
- Assigned resources to the task
- Set priorities for all the tasks
The start date of my project is in the future and the resources are no
assigned to any other resource. The only reason I set their availabilit
to e.g. 40% is because they also still have their dayly job to do.
Now I want MS Project to propose me a planning and to schedule th
tasks in time based on priority, and availability of resources. When
use Tools > Level resources, it doesn't do exactly what I want it t
do.
- It complains about overallocation for some resources, but that i
just what I want the tool to resolve. If person A is at 200% in m
resource graph, I want MS project to reshuffle the tasks to resolv
that, but it gives an error that it cannot do that.
- The tasks with highest priority are not always done first.
- Some tasks gest split up in a very strange way, like a part today
a little in two weeks, and finishing the rest in 7 weeks, even is
uncheck the checkbox that it can split tasks.
Basically, I want to know what is the earliest we can finish th
project giving the resources we have. Am I doing it the right way? An
suggestions?
Thanks
Cedri
I'm just starting out with MS project 2007 and I have something I can'
get right.
I have already
- Created my resources and stated how many % they are available fo
the project, e.g. 40% (2 days per week)
- Listed all my tasks
- Added an estimate of how many hours a task would take in the wor
column (I didn't touch the duration, start or finish columns)
- Assigned resources to the task
- Set priorities for all the tasks
The start date of my project is in the future and the resources are no
assigned to any other resource. The only reason I set their availabilit
to e.g. 40% is because they also still have their dayly job to do.
Now I want MS Project to propose me a planning and to schedule th
tasks in time based on priority, and availability of resources. When
use Tools > Level resources, it doesn't do exactly what I want it t
do.
- It complains about overallocation for some resources, but that i
just what I want the tool to resolve. If person A is at 200% in m
resource graph, I want MS project to reshuffle the tasks to resolv
that, but it gives an error that it cannot do that.
- The tasks with highest priority are not always done first.
- Some tasks gest split up in a very strange way, like a part today
a little in two weeks, and finishing the rest in 7 weeks, even is
uncheck the checkbox that it can split tasks.
Basically, I want to know what is the earliest we can finish th
project giving the resources we have. Am I doing it the right way? An
suggestions?
Thanks
Cedri