M
Mark Kampe
I have what I believe to be an extremely common situation.
I have a dozen programmers. For the purpose of this question, assume them
to be interchangeable. Each has his own availability (due to hiring dates,
other projects, ramp-up times) which I think I know how to represent in the
resource information. Each also has assorted other obligations (support,
review participation, meetings, etc) that I also think I know how to
represent as tasks. All of these people are capable of a reasonable degree
of multi-tasking. I also have a bunch of new development tasks that need
doing, and to a first approximation it doesn't matter who does which of them.
I would love to be able to tease Project into assigning tasks to resources,
based on the available time that each resource has. I haven't seen a way to
do this.
I can make my own assignments, but I have to specify how much each person
will work on the task. This is not a fixed number ... as each person has a
different number of available hours each week (due to availability dates,
ramp-ups, and other responsibilities). I would at least like to get Project
to apply "the available hours" to a task ... but I cannot find a way to do
this either.
Essentially, it seems that I have to decide who will work, how much, on each
task, starting when ... after which Project will be happy to print beautiful
reports. Figuring out who should work, on which task, starting when, seems
to be my problem. This seems a pretty common problem (it is one I've had
continuously for the last thirty years) and yet I can't find discussions of
it, nor have I seen sample projects that seem to address these issues.
In a (surely different, but) related problem, I have deliberately assigned
only a small fraction of a person to a task (knowing that they will have at
least that much time available). Whether the task is fixed unit or fixed
work, I often find that
applying someone 10% time to a 25 day task, results in them doing four hours
per week of work for five weeks after which the task is shown as completed
.... (in only 20 hours of work). Apparently I don't understand when a
duration is a start-to-end day count, and when duration is a number of
staff-days.
I have a dozen programmers. For the purpose of this question, assume them
to be interchangeable. Each has his own availability (due to hiring dates,
other projects, ramp-up times) which I think I know how to represent in the
resource information. Each also has assorted other obligations (support,
review participation, meetings, etc) that I also think I know how to
represent as tasks. All of these people are capable of a reasonable degree
of multi-tasking. I also have a bunch of new development tasks that need
doing, and to a first approximation it doesn't matter who does which of them.
I would love to be able to tease Project into assigning tasks to resources,
based on the available time that each resource has. I haven't seen a way to
do this.
I can make my own assignments, but I have to specify how much each person
will work on the task. This is not a fixed number ... as each person has a
different number of available hours each week (due to availability dates,
ramp-ups, and other responsibilities). I would at least like to get Project
to apply "the available hours" to a task ... but I cannot find a way to do
this either.
Essentially, it seems that I have to decide who will work, how much, on each
task, starting when ... after which Project will be happy to print beautiful
reports. Figuring out who should work, on which task, starting when, seems
to be my problem. This seems a pretty common problem (it is one I've had
continuously for the last thirty years) and yet I can't find discussions of
it, nor have I seen sample projects that seem to address these issues.
In a (surely different, but) related problem, I have deliberately assigned
only a small fraction of a person to a task (knowing that they will have at
least that much time available). Whether the task is fixed unit or fixed
work, I often find that
applying someone 10% time to a 25 day task, results in them doing four hours
per week of work for five weeks after which the task is shown as completed
.... (in only 20 hours of work). Apparently I don't understand when a
duration is a start-to-end day count, and when duration is a number of
staff-days.