Automatic updation of project milestones in program workplan

  • Thread starter Vidya Narasimhan
  • Start date
V

Vidya Narasimhan

Hello,

I am creating a program workplan that has atleast 3 project workplans
embedded in it. I am trying to track progress on the program (at a summary
level) with milestones of the project workplan. If the project workplan
milestones are updated in the larger program workplan, is there a way I can
link the project milestones in the program workplan, so that when the project
milestones are updated, the summary level of the program workplan will
update without having to manually update the program workplan?

Thanks,

Vidya
 
J

John

Vidya Narasimhan said:
Hello,

I am creating a program workplan that has atleast 3 project workplans
embedded in it. I am trying to track progress on the program (at a summary
level) with milestones of the project workplan. If the project workplan
milestones are updated in the larger program workplan, is there a way I can
link the project milestones in the program workplan, so that when the project
milestones are updated, the summary level of the program workplan will
update without having to manually update the program workplan?

Thanks,

Vidya

Vidya,
You don't say exactly how you are creating the upper level workplan
although you do use the term "embedded". From that I might assume that
you have a master project with the 3 workplans inserted as subprojects.

You also mention that you are trying to track progress at the summary
level with milestones. I'm not sure exactly what that means. If you are
trying to force the milestones at a summary level to link to the
subprojects then you are probably gong about it incorrectly.

Here is what I suggest. It's not quite clear where you want the
milestones to reside (i.e. in the master or in the subprojects), however
let's assume the milestones are in the master (i.e. upper level plan).
Then use external links (i.e. external predecessors) to link those
milestones to each of the subprojects. Then, whenever the milestones are
updated, the link will drive that change down to the subprojects.

John
Project MVP
 
V

Vidya Narasimhan

John,

Thanks for your response.

Your are correct in your assumption that the master project plan will
include the 3 sub projects.

Ideally, I want the milestones to reside in the upper level (master) project
plan as well as in the lower level detailed sub-project plan.

Are the external predecessors same as the predecessors?

Here is some additional information that might hep you better understand my
situation - the 3 sub-projects will be handled by 3 different people and one
person (other then the 3 sub-project managers) will handle the master project
plan (upper level). On a weekly basis, the sub-projects will be updated by
the sub-project managers and the master project manager will copy and paste
the updated sub-project plan (lower level) in the approriate place in the
master project plan. Since the milestones reside at the upper level and at
the lower level, once the updated sub-project plan is pasted at the lower
level, can the milestones in the upper level be automatically updated by such
external predecessors links?

Thanks very much for your response,

best regards

Vidya
 
J

John

Vidya Narasimhan said:
John,

Thanks for your response.

Your are correct in your assumption that the master project plan will
include the 3 sub projects.

Ideally, I want the milestones to reside in the upper level (master) project
plan as well as in the lower level detailed sub-project plan.

Are the external predecessors same as the predecessors?

Here is some additional information that might hep you better understand my
situation - the 3 sub-projects will be handled by 3 different people and one
person (other then the 3 sub-project managers) will handle the master project
plan (upper level). On a weekly basis, the sub-projects will be updated by
the sub-project managers and the master project manager will copy and paste
the updated sub-project plan (lower level) in the approriate place in the
master project plan. Since the milestones reside at the upper level and at
the lower level, once the updated sub-project plan is pasted at the lower
level, can the milestones in the upper level be automatically updated by such
external predecessors links?

Thanks very much for your response,

best regards

Vidya
Vidya,
You were fine until you mentioned cut and paste. That is NOT the best
way to create a master project. What you should do is use Insert/Project
to insert the 3 subproject plans into a master file. That automatically
creates a dynamic master wherein changes at either the master level or
at the subproject levels will be reflected in the other. It is best to
have the master and all 3 subproject residing on a single common server
where everybody has read/write access.

External predecessors are the same as predecessors except the link
includes the path to the other file.

The foremost question is, who has responsibility for each milestone? Is
it the manager at the lower level plan or the manager of the upper level
plan? It can't be both. The actual milestone should reside in the
"owner's" plan. I'm guessing that the milestones should be in each of
the lower level plans. Then, create an external link from that milestone
to a duplicate milestone in the master plan. With a master plan it is
very easy to create the external links using a drag and drop process.
That is, select the Gantt milestone at the lower level and with the
mouse button held down, drag it up to the duplicate milestone in the
master. An external link will be formed. You can filter the master to
make it easier to see both milestones on a single screen. Or, go the the
project help file and read about external links.

Once the link is made, when the lower level managers update their
milestone, that change will automatically be updated in the master.

Hope this helps.
John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top