K
krt005
Hi,
I have the following scenario:
Created a task with a duration of 32 hrs (4 days) and assigned resource A to
work on that task. Later i added resource B to the same task. Total work of
the task remained 32 hrs but duration went down to 16 hrs (2 days) as
expected.
I then set resource B to start working a day later than the task's start
date. Duration was increased to 24 (3 days) hrs but i'm left with Resource A
doing nothing on the 3rd day. Is there a way to set Project to automatically
adjust working time of resources so that the task finishes asap. In my
scenario what i would have liked to achieve is to set Project to
automatically adjust working time of resource B to 12 hrs and resource A to
20 hrs. Like this, on the 3rd day both will work for 4hrs and the task will
finish by mid-day, and not end of day.
Hope i explaned myself clearly.
Thanks in advance
I have the following scenario:
Created a task with a duration of 32 hrs (4 days) and assigned resource A to
work on that task. Later i added resource B to the same task. Total work of
the task remained 32 hrs but duration went down to 16 hrs (2 days) as
expected.
I then set resource B to start working a day later than the task's start
date. Duration was increased to 24 (3 days) hrs but i'm left with Resource A
doing nothing on the 3rd day. Is there a way to set Project to automatically
adjust working time of resources so that the task finishes asap. In my
scenario what i would have liked to achieve is to set Project to
automatically adjust working time of resource B to 12 hrs and resource A to
20 hrs. Like this, on the 3rd day both will work for 4hrs and the task will
finish by mid-day, and not end of day.
Hope i explaned myself clearly.
Thanks in advance