I
Iain Carlin
Hi,
I have a macro that creates a new project each month based on a default
template for that project.
The macro needs to reschedule all the tasks bases on the first day of the
month. I can do this manually using the Adjust Dates button on the Analysis
Toolbar.
Question is, how do I achieve the same thing as Adjust Dates is doing, but
from within my macro?
Thanks,
Iain Carlin
I have a macro that creates a new project each month based on a default
template for that project.
The macro needs to reschedule all the tasks bases on the first day of the
month. I can do this manually using the Adjust Dates button on the Analysis
Toolbar.
Question is, how do I achieve the same thing as Adjust Dates is doing, but
from within my macro?
Thanks,
Iain Carlin