Quick follow up question related to this topic:
When using fixed duration tasks w/ remaining work set to 0 (i.e. 100% complete),
any change to the remaining work will reset the duration of the task in MPP.
Therefore, in MPP, if I want to enter time against an unfinished task, increase
remaining work, and not change duration, I would have to:
First: Enter new remaining work
Second: Enter hours against the task (actual work)
and would not change the duration of the task.
Example
Task A:
Duration = 2d
Work = 16h
I enter 16h against the task, then change the remaining hours to 8h, thus
changing overall work to 24h.
If I enter (and apply) 16h against the task, that drives the %complete to
100%. Now, when I change the remaining hours (and apply them), it changes
duration.
The question then is how is this quirk handled in the sync between PWA timesheets
and the scheduling engine? It would seem to me that the sync would occur
in a batch and would have to first apply the new remaining hours before applying
actual work to avoid changing duration. If it syncs the actuals first, and
then the remaining work, that might cause duration to change.
Would there be any change in project behavior along these lines if I went
to managed periods?
Thks...
-A