M
Mike
Hi
Every day, I have to open de project file, go to "Tools->Tracking->Update
Project".
I select "Update work as complete through" with "Set 0% - 100% complete"
option.
I have to change de "Date" and press ok.
Is there a way to do this automatically.
Is there a way to do this even without open de projecto file?
Thanks a lot.
Every day, I have to open de project file, go to "Tools->Tracking->Update
Project".
I select "Update work as complete through" with "Set 0% - 100% complete"
option.
I have to change de "Date" and press ok.
Is there a way to do this automatically.
Is there a way to do this even without open de projecto file?
Thanks a lot.