B
bradsaxon
When I update the resource units for an individual activity, it does not
automatically update the work column. What am I missing? Is there a setting
to make Work update automatically?
For example, I have 4 resources assigned to complete a task. When I update
the resource allocation (from 3% to 6%), the Work task does not change. Also,
when I "Clear Contents" WOrk returns to 0 and I can't get the Work total to
update.
Thanks for the help!
Brad
automatically update the work column. What am I missing? Is there a setting
to make Work update automatically?
For example, I have 4 resources assigned to complete a task. When I update
the resource allocation (from 3% to 6%), the Work task does not change. Also,
when I "Clear Contents" WOrk returns to 0 and I can't get the Work total to
update.
Thanks for the help!
Brad