I currently manage a Master Schedule with 20 consolidated
projects linked to a resource pool. I would like to
create an auto backup feature for the PMs.

How do I write the code so that the link to resource pool
is automatically broken before backing up and reconnected
after backup completes.

thanks
 
R

Rod Gill

Hi,

If your Network backup won't do this, then I would simply Zip the folder
regularly.

--
Rod Gill