Is it possible to trigger a VBA procedure when, in Project Pro, the user
changes the value of an Outline Enterprise Project Text code ?
Thanks ahead
 
R

Rod Gill

Not for a specific field. However there is a Task Change event that has a
column parameter you can test. However, this event may not reliably trigger
depending on how the task is updated. You will need to experiment.
 
N

Newbie

Rod,
I'm afraid the Task Change event will not work : I need to test when the
user changes the value of a Project field... ;-(
 