When I insert the 'Availability' field on portfolio analyzer views where we
have "Resource" and "Projects" as Row Fields, many projects are displayed
under a resource's name that they are not assigned to or even on the project
team. If I remove the Availability field, then only the projects that
resources have assignments in are displayed under their names. We have
several views that utilize this Availabilty field. Is this a known bug and is
there a fix?
Thank you-
have "Resource" and "Projects" as Row Fields, many projects are displayed
under a resource's name that they are not assigned to or even on the project
team. If I remove the Availability field, then only the projects that
resources have assignments in are displayed under their names. We have
several views that utilize this Availabilty field. Is this a known bug and is
there a fix?