Availability in an Enterprise Field

V

Veronica

Hi,
I want to summarize all resources (used in a specific project) availability
for using the amount in a calculated enterprise field. But I can´t find the
availibility field when making the formula.
Does anyone know how to do it? Or where to find it?
(I need it for measuring the allocation rate on project level)
Thank´s
/Veronica
 
G

Gary L. Chefetz [MVP]

Veronica:

Availability needs to be calculated against the resource calendar. Total
availability is calculated in hours across a defined number of days, weeks,
months, years, etc. So, you can't find availability as an available field in
Project. If you're trying figure utilization in a specific project for
specific resources, you can do this very easily in the Portfolio analyzer.
The analyzer was made for this type of reporting.
 