I
Iona
Hello,
Please don't think me silly. I am a new user to Project Professional 2007
and I love it thus far. I am seeking a solution or some direction on how to
go about my request below.
I have 50 Summary Tasks with 20 SubTasks that I track. I am looking to
obtain an average number of days it takes to start these specific tasks by
quarter. Can I do this in project? I was able to do a pivot into excel and
get my results. But I can't find anything in Project Help. So I am coming to
the Experts!
PS I have these tasks Marked and as Milestones.
Example:
Job Start (20 Job Starts that range from 7/1/08 - 6/30/09)
Construction Complete (" ")
Design Approval
etc....
Desperate for help - Thanks so much for anytime or input Iona
Please don't think me silly. I am a new user to Project Professional 2007
and I love it thus far. I am seeking a solution or some direction on how to
go about my request below.
I have 50 Summary Tasks with 20 SubTasks that I track. I am looking to
obtain an average number of days it takes to start these specific tasks by
quarter. Can I do this in project? I was able to do a pivot into excel and
get my results. But I can't find anything in Project Help. So I am coming to
the Experts!
PS I have these tasks Marked and as Milestones.
Example:
Job Start (20 Job Starts that range from 7/1/08 - 6/30/09)
Construction Complete (" ")
Design Approval
etc....
Desperate for help - Thanks so much for anytime or input Iona