A
Andplas
I ' m trying to figure out the following.
I have a sequence of 4 tasks each one linked to another on a FS
relationship. The fourth task is a deadline and has a constraint ''Must
Finish On''. Between the third and fourth task there is a slack.
If i try to extend the duration of the first task by exceeding the available
slack I receive a message if i want to allow or avoid the scheduling conflict
..
I press OK - ''Cancel and avoid the scheduling conflict'', and duration of
the first task returns to its original value.
If i try again to extend the duration by the same amount i receive no
message - the link between my first task and the second one no longer exists
(although i can see it in the predecessors column!!!!) and the first task has
moved far away from the deadline. Why this is happened?
Should the programm notify me again about the new conflict or not??
I have a sequence of 4 tasks each one linked to another on a FS
relationship. The fourth task is a deadline and has a constraint ''Must
Finish On''. Between the third and fourth task there is a slack.
If i try to extend the duration of the first task by exceeding the available
slack I receive a message if i want to allow or avoid the scheduling conflict
..
I press OK - ''Cancel and avoid the scheduling conflict'', and duration of
the first task returns to its original value.
If i try again to extend the duration by the same amount i receive no
message - the link between my first task and the second one no longer exists
(although i can see it in the predecessors column!!!!) and the first task has
moved far away from the deadline. Why this is happened?
Should the programm notify me again about the new conflict or not??