G
Gio
Hi there,
On the calculations tab in Options I've deselected the
checkbox for Updates to Task status updates resource
status and so I though that when I entered task progress
that it would never generate actual work values but to my
suprise there were some instances where it did.
Example1: When I mark a task as 100% actual hours are
entered.
Example2: Assume an unstarted task with a duration of 5
days. Now you update the task to indicate an actual
duration of 6 days and a remaining duration of 2 days.
Project enters actual hours for the first 6 days even
though I set the option not to!
Are there other exceptions and can one avoid this/turn of
the calculation of actual hours completely?
On the calculations tab in Options I've deselected the
checkbox for Updates to Task status updates resource
status and so I though that when I entered task progress
that it would never generate actual work values but to my
suprise there were some instances where it did.
Example1: When I mark a task as 100% actual hours are
entered.
Example2: Assume an unstarted task with a duration of 5
days. Now you update the task to indicate an actual
duration of 6 days and a remaining duration of 2 days.
Project enters actual hours for the first 6 days even
though I set the option not to!
Are there other exceptions and can one avoid this/turn of
the calculation of actual hours completely?