A
aernoud
Hi,
I am trying to avoid tasks being split.
I have a couple of subtasks in my current planning assigned to a certain
resource (in this case a video encoding machine) that are being interrupted
to perform the same task, listed under another main task. After wich it goes
back to the task it had already started.
I understand that this is the 'fastest' way to complete the overall project,
but since we are working with encoding machines that work best if they can
finish a job from start to end at once, I would like to avoid splitting those
tasks.
Setting a fixed date for the beginning of this task does do the job,
however, this messes with the dynamics of the planning so I would like to
avoid that (my planning often changes, tasks never take the same time).
I have been trying to find out how to achieve this, but until now without
succes. Does anybody know of a way to do this?
Any help would be greatly appreciated!!
Kind regards,
Aernoud
The Netherlands
I am trying to avoid tasks being split.
I have a couple of subtasks in my current planning assigned to a certain
resource (in this case a video encoding machine) that are being interrupted
to perform the same task, listed under another main task. After wich it goes
back to the task it had already started.
I understand that this is the 'fastest' way to complete the overall project,
but since we are working with encoding machines that work best if they can
finish a job from start to end at once, I would like to avoid splitting those
tasks.
Setting a fixed date for the beginning of this task does do the job,
however, this messes with the dynamics of the planning so I would like to
avoid that (my planning often changes, tasks never take the same time).
I have been trying to find out how to achieve this, but until now without
succes. Does anybody know of a way to do this?
Any help would be greatly appreciated!!
Kind regards,
Aernoud
The Netherlands