AW in OLAP report different to Project Schedule

R

riccadonna63

Hello

Over the last week I have noticed that the AW hours in the OLAP are
different to the project schedule. eg. schedule shows 5 hrs on 31
July but those 5 hrs don't show up in the OLAP. We are using PS2003
and I have already done the following:

- Sync to protected actuals function in the schedule
- Made a change and then resubmitted the timesheet, got the PM to
approve the tasks and rebuilt the OLAP cube

All the updates have been done as hours in August are all there. It
seems to be hours for just one day (different day in the various
schedules). The resources are all committed.

I appreciate any ideas on what I can try or where I can start to
look. I am now starting to worry that the same issue applies to more
schedules than I am aware of.

Thank you for your help

Rosa
 
R

riccadonna63

Hello

Over the last week I have noticed that the AW hours in the OLAP are
different to the project schedule.  eg.  schedule shows 5 hrs on 31
July but those 5 hrs don't show up in the OLAP.  We are using PS2003
and I have already done the following:

- Sync to protected actuals function in the schedule
- Made a change and then resubmitted the timesheet, got the PM to
approve the tasks and rebuilt the OLAP cube

All the updates have been done as hours in August are all there.  It
seems to be hours for just one day (different day in the various
schedules).  The resources are all committed.

I appreciate any ideas on what I can try or where I can start to
look.  I am now starting to worry that the same issue applies to more
schedules than I am aware of.

Thank you for your help

Rosa

Hi

Can anyone help me with this. I'm really desperate and don't know
where else to look.

Thanks
Rosa
 