DJ Huff
I am recasting the way we manage our mega-project using MSP 2003 (there
previously ws no project plan, used Excel) and we want to display EV metrics.
We recasted the plans mid-project, which means that many tasks began well
before the "go live" date for using the MSP. We are capturing actuals, but
not for previous dates. EV metrics show negative values when they may not be
if we had actuals filled in for previous days' work. I cannot copy/paste
Work into Actual Work.
How do I backfill the Actual Work for previous tasks? We do not want to
change the Project Begin Date.
Also...I have the plans set up as Fixed Duration. I know the three elements
that can change based upon what you do with one or more of the other
elements, but it is real confusing and hard to keep up with. Managers
complain that resource % change and Work is distributed throughout the plan
tasks without input from the managers except by changing duration or Finish
dates. Should I change to Fixed Unit/Effort Driven so that resource % don't
change? If so, then how do I also control the distribution of hours over the
Work element of tasks?
previously ws no project plan, used Excel) and we want to display EV metrics.
We recasted the plans mid-project, which means that many tasks began well
before the "go live" date for using the MSP. We are capturing actuals, but
not for previous dates. EV metrics show negative values when they may not be
if we had actuals filled in for previous days' work. I cannot copy/paste
Work into Actual Work.
How do I backfill the Actual Work for previous tasks? We do not want to
change the Project Begin Date.
Also...I have the plans set up as Fixed Duration. I know the three elements
that can change based upon what you do with one or more of the other
elements, but it is real confusing and hard to keep up with. Managers
complain that resource % change and Work is distributed throughout the plan
tasks without input from the managers except by changing duration or Finish
dates. Should I change to Fixed Unit/Effort Driven so that resource % don't
change? If so, then how do I also control the distribution of hours over the
Work element of tasks?