backup formulas

J

John

Lynn said:
how do I backup and restore formulas in mpp file?

Lynn,
Unlike macros, formulas in custom fields are unique to the containing
Project file (i.e. they don't reside in the Global file). You can "back
up" your formulas by saving the file as a template but if you want to
use those same formulas in another new project file, you will need to
copy and paste, unless you can adapt the template directly for you new
project.

John
Project MVP
 
A

Andrew

I have a "standard" programme in which I import any formulas and customised
fields. you can then open up any new programme and import formulas. or just
copy & rename the blank standard

Andrew
 
G

Gérard Ducouret

Lynn,

If you are not connected to Project Server 2007, you are able to copy your
calculated field in your Global.MPT file via the Organizer:
Tools / Organizer... / Fields

Gérard Ducouret
 