Backward pass

R

richard.craven

Dale said:
Does MS Project perform a backward pass?

Yes it does. If you insert Early Finish and Late Finish Columns you can see
that both the forward and backward pass have been performed.

Richard Craven
 
G

Gérard Ducouret

Hello,
One more detail to Richard answer :
To set the backward scheduling in MS Project, go to Project / Project
Information... Schedule from : Project Finish Date

Hope this help,

Gérard Ducouret
 
M

Mike Glen

Project carries out both forward and backward passes - that's how it
calculates the critical path. However, don't schedule backwards from the
finish as every task is then critical and you've lost all flexibility!

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top