B
Bohus
I have 34 entries in my project and project duration is 24 days. I assigned
resources and tried what is what in menu and since then I have one problem.
If I select 'Project/Filter by critical' from menu I see only 2 tasks which
take 3 days and it is absolutely bad. MSP doesn't show my correct critical
path.
What's wrong ?
(Until that I had 12 entries in critical path. Everything looks O.K. until I
select critical from menu.)
resources and tried what is what in menu and since then I have one problem.
If I select 'Project/Filter by critical' from menu I see only 2 tasks which
take 3 days and it is absolutely bad. MSP doesn't show my correct critical
path.
What's wrong ?
(Until that I had 12 entries in critical path. Everything looks O.K. until I
select critical from menu.)