B
bobmcl
I would like to superimpose milestones on the Gantt bar displayed for each
project summary in a project center view. This can be done for a single
project within Project Professional by flagging the milestone as "Roll up
Gantt bar to summary" and then setting the correct conditions in Format > Bar
Styles > Show for ...Tasks.
I would like to do the same thing in a project center view - display the
milestone icon for the rolled up milestone task superimposed on the Gantt bar.
I appreciate any help.
Thanks,
Bob
project summary in a project center view. This can be done for a single
project within Project Professional by flagging the milestone as "Roll up
Gantt bar to summary" and then setting the correct conditions in Format > Bar
Styles > Show for ...Tasks.
I would like to do the same thing in a project center view - display the
milestone icon for the rolled up milestone task superimposed on the Gantt bar.
I appreciate any help.
Thanks,
Bob