N
nmorph
I am trying to format the bar styles in the detail Gantt view to show green
for on time, yellow for close to due date and red for past due. First, what
is the best way to show these in the bar styles dialog box? Second, do these
have to manually be updated?
Also, I have entered a column for schedule status that shows green, yellow
and red graphical indicators. I notice that they are often incorrect. The
formula I have entered is: IIf([% Complete]<100 And [Finish]<[Current
Date],"Red",IIf([% Complete]>50 And [% Complete]<100 And [Finish]>[Current
Date]-10,"Yellow","Green")). Do these have to be manually updated?
Thanks!
for on time, yellow for close to due date and red for past due. First, what
is the best way to show these in the bar styles dialog box? Second, do these
have to manually be updated?
Also, I have entered a column for schedule status that shows green, yellow
and red graphical indicators. I notice that they are often incorrect. The
formula I have entered is: IIf([% Complete]<100 And [Finish]<[Current
Date],"Red",IIf([% Complete]>50 And [% Complete]<100 And [Finish]>[Current
Date]-10,"Yellow","Green")). Do these have to be manually updated?
Thanks!