B
Bart
If I customize an enterprise task field of the type Date, then I cannot use
this field to define a Bar Style in an enterprise view. Apparently, this
customized date field value is not picked up by the client becasue I cannot
show it on existing styles as a detail (left,right,top,bottom,inside), nor
can I draw a placeholder on such a date.
Is this a Known issue?
I use the 2003 SP2 version of Project Professional with a 2003 server SP2a
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...867c-9312806a7a4e&dg=microsoft.public.project
this field to define a Bar Style in an enterprise view. Apparently, this
customized date field value is not picked up by the client becasue I cannot
show it on existing styles as a detail (left,right,top,bottom,inside), nor
can I draw a placeholder on such a date.
Is this a Known issue?
I use the 2003 SP2 version of Project Professional with a 2003 server SP2a
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...867c-9312806a7a4e&dg=microsoft.public.project