Bar styles based on Task Enterprise Date fileds do not work

B

Bart

If I customize an enterprise task field of the type Date, then I cannot use
this field to define a Bar Style in an enterprise view. Apparently, this
customized date field value is not picked up by the client becasue I cannot
show it on existing styles as a detail (left,right,top,bottom,inside), nor
can I draw a placeholder on such a date.

Is this a Known issue?

I use the 2003 SP2 version of Project Professional with a 2003 server SP2a

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...867c-9312806a7a4e&dg=microsoft.public.project
 
J

JulieS

Hello Bart,

As you have not yet received an answer in this newsgroup and your
question concerns Project Server, I suggest you re-post your
question to the project server newsgroup
(microsoft.public.project.server) if you haven't already posted there.

Although most of the folks who answer questions in the newsgroups visit
all the groups, I think there's a higher concentration of "server gurus"
there and you may get a quicker answer.

I hope this helps.

Julie
Project MVP
 