D
Dave
I have a created a custom view in Enterprise Global that shows
milestones in the way management wants to see them - that works fine -
I can open any project and appy that view. Recently, I wanted certain
milestones to be "color coded" based on an Enterprise Flag. When I
open the "Bar Styles ..." window on the Gantt Chart, the "Show for ...
Tasks" column only lets me select what I guess you'd call project level
flag fields (e.g. Flag1, Flag2, etc.) - not Enterprise Flag fields. I
can go into an individual project and make the Flag1 field equal to the
Enterprise Flag field that I want and get the effect I want, but I have
to do open each project and edit the Flag1 field to do it. The
question is, how do I automatically get a "project level" flag to equal
an enterprise flag whenever a project is opened? (or is there a better
way to do this?)
Thanks,
Dave
milestones in the way management wants to see them - that works fine -
I can open any project and appy that view. Recently, I wanted certain
milestones to be "color coded" based on an Enterprise Flag. When I
open the "Bar Styles ..." window on the Gantt Chart, the "Show for ...
Tasks" column only lets me select what I guess you'd call project level
flag fields (e.g. Flag1, Flag2, etc.) - not Enterprise Flag fields. I
can go into an individual project and make the Flag1 field equal to the
Enterprise Flag field that I want and get the effect I want, but I have
to do open each project and edit the Flag1 field to do it. The
question is, how do I automatically get a "project level" flag to equal
an enterprise flag whenever a project is opened? (or is there a better
way to do this?)
Thanks,
Dave