C
Chris.
I have read various topics and they seem to confirm that you cannot change
the appearance of bars spanning non working time. This is a fundamental
presentation requirement.
At a basic level, I have some tasks that can work over Ramadan and some that
cannot. It appears that I have only 2 opitons. Either all activities appear
to work over Ramadan or all appear not to using the "in front" or "behind"
setting for non working time.
The only way of getting around this appears to be to have seperate projects
for different calendars and have the non working time shading in fornt of the
task bars. This is not a great solution as the visual flow of logic is lost.
Surely MS are going to create a setting that allows task bars to "neck" or
simlpy not span the non working time according to the calendar assigned to
them.
Please let me know is this is available and I simply can't find the setting!!!
Thanks in advance.... Chris.
the appearance of bars spanning non working time. This is a fundamental
presentation requirement.
At a basic level, I have some tasks that can work over Ramadan and some that
cannot. It appears that I have only 2 opitons. Either all activities appear
to work over Ramadan or all appear not to using the "in front" or "behind"
setting for non working time.
The only way of getting around this appears to be to have seperate projects
for different calendars and have the non working time shading in fornt of the
task bars. This is not a great solution as the visual flow of logic is lost.
Surely MS are going to create a setting that allows task bars to "neck" or
simlpy not span the non working time according to the calendar assigned to
them.
Please let me know is this is available and I simply can't find the setting!!!
Thanks in advance.... Chris.