Base Calendar Error In Enterprise Resource Pool

L

Latric23

Hi,

I am using Project Server 2003 and Project Pro 2003 with SP1. There are
over 1200 resources in a resource pool that had different base calendars set
last week. In the resource pool, the list of base calendars is the default
"Standard" calendar along with two custom enterprise calendars. After
opening the resource pool, I noticed all calendars for resources had
mysteriously changed to the default "Standard" calendar. Does anyone know
what changes could have been made, that would cause all base calendars for
all resources in an enterprise resource pool to change to "Standard" and if
the base calendars that were set for each resource can be restored?
 