I am using MSP 2013. I set up my project with a 24hr calendar and have adjusted the Project Options/Schedule/Defaults to reflect that.
I have created resources with dedicated calendars of 8hr and/or 10hr. When i assign resources the applicable resource calendar should be initiated for that task. How can i verify that?
I am having issues with the resource calendar not displacing the project calendar when i assign the resources.
When i go to Task Information/Advanced/Calendar the applied resource calendar does not show. i get either 24hr or none in the Task Information/Advanced/Calendar cell.
Do i have to manually set the calendar for each task using the Task Information/Advanced/Calendar?
I have created resources with dedicated calendars of 8hr and/or 10hr. When i assign resources the applicable resource calendar should be initiated for that task. How can i verify that?
I am having issues with the resource calendar not displacing the project calendar when i assign the resources.
When i go to Task Information/Advanced/Calendar the applied resource calendar does not show. i get either 24hr or none in the Task Information/Advanced/Calendar cell.
Do i have to manually set the calendar for each task using the Task Information/Advanced/Calendar?