Base Calendars in Project Server 2007

D

Dale Howard [MVP]

Savoy55 --

Log into PWA with Administrator permissions and then click Server Settings -
Additional Server Settings. Select the "Allow projects to use local base
calendars" option and click the Save button. Hope this helps.
 
S

Savoy55

Dale, Thanks. That did the trick.

Dale Howard said:
Savoy55 --

Log into PWA with Administrator permissions and then click Server Settings -
Additional Server Settings. Select the "Allow projects to use local base
calendars" option and click the Save button. Hope this helps.
 