Base Duration

G

Girija

Hello,

I have baselined a project and found that the Baseline duration field
contains the information as planned. But when I changed the planned duration,
Baseline Duration field, didnt update this. Can anyone tell me how do I
update the Baseline Duration with the latest duration information?

Thanks

Girija
 
B

Ben Howard

Hello,
The baseline information won't automatically update, otherwise there would
be no point in having the baseline (which is a reference of the schedule at a
point in time). In order to update the baseline, select the existing
baseline and click baseline. You will be prompted to override the existing
baseline.
 