G
Girija
Hello,
I have baselined a project and found that the Baseline duration field
contains the information as planned. But when I changed the planned duration,
Baseline Duration field, didnt update this. Can anyone tell me how do I
update the Baseline Duration with the latest duration information?
Thanks
Girija
I have baselined a project and found that the Baseline duration field
contains the information as planned. But when I changed the planned duration,
Baseline Duration field, didnt update this. Can anyone tell me how do I
update the Baseline Duration with the latest duration information?
Thanks
Girija