R
Ryan
Dear all,
When I tried to open an existing project and view the Resource Usage, the
Base. Work for all the tasks under an resource have values. However, the
Base. Work on the resource's name's row does not show the accumulated value
for all tasks while Work and Act. Work have the accumulated values. I found
the solution is simply to reset the baseline. However, it seems the value was
lost again when next time I open the project again. Does any one know apart
from setting the baseline each time I open the project, any way to make it
show the accumulated value for the tasks on the resources? Thanks in advance.
Best Regards,
Ryan
When I tried to open an existing project and view the Resource Usage, the
Base. Work for all the tasks under an resource have values. However, the
Base. Work on the resource's name's row does not show the accumulated value
for all tasks while Work and Act. Work have the accumulated values. I found
the solution is simply to reset the baseline. However, it seems the value was
lost again when next time I open the project again. Does any one know apart
from setting the baseline each time I open the project, any way to make it
show the accumulated value for the tasks on the resources? Thanks in advance.
Best Regards,
Ryan