Baseline cash flow report does not match baseline budget.

K

kraus

I'm trying to run a report showing my baseline cash flow over the life of the
project. For some reason, the report for the baseline cash flow total is
less than the report for the baseline budget. The baseline budget does show
the correct amount.

I have checked my date ranges to ansure I am capturing the same data on both
reports and I am. I did find a task that was baselined past the finish date
and I have since adjusted that to bring it back in line but I don't know what
else to do to resolve the difference.

Any help would be appreciated.

David
 
K

kraus

Update...when I compare the two reports in hard copy, I can see the 3 tasks
that make up the difference and in the cash flow report, the task is
identified but the amount is not showing for some reason. Help.
 
K

kraus

I'm not sure if that't the problem because the line item does have the cost
showing with it. If it was assigned to the summary then I wouldn't have
expected to see it next to the task as well.

Nonetheless, I deleted the task and re-entered it and the world seems to be
a better place now. Problem resolved...or...bandaid applied, not sure which.
But any other comments/suggestions would be welcome.
 